EMS Facility Renovations

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print
Three side by side renderings of three EMS Stations that will receive renovations.

Location: Eight Dare County EMS stations throughout Dare County

Phase 1: EMS Station 1 (Kill Devil Hills), EMS Station 4 (Southern Shores) and EMS Station 7 (Dare MedFlight Hangar on Roanoke Island) 

Start Date: March 2023

Projected Completion: July 2024

Estimated Cost:
Approximately $42.9 million

EMS Project Details

Phase One:

EMS Station 1 - Kill Devil Hills
Image of the exterior of EMS Station 1 under construction with the Kill Devil Hills water tower in the background.
Image of the exterior of EMS Station 1 under construction.
Rendering of the new EMS Station 1 facility.
Images showcasing construction progress on EMS Station 1.
Images showcasing construction progress on EMS Station 1.
Image of a row of people digging sand for the EMS Station 1 Groundbreaking Ceremony.

EMS Station 4 - Southern Shores
Image of EMS Station 4 exterior in progress, featuring large blue doors.
Image of EMS Station 4 exterior in progress.
Rendering of the Southern Shores EMS Station 4 building.
Image of interior bathroom at EMS Station 4.
Image of county and town officials breaking ground on the future Dare County EMS Station 4 & Southern Shores Fire Department site.

EMS Station 7 - MedFlight Hangar
Construction progress on the exterior of the EMS Station 7 facility.
Image of the construction progress inside the new EMS Station 7 facility.
Rendering of the EMS Station 7 building.
Image of construction underway on EMS Station 7.
Image of interior construction underway on EMS Station 7.


Phase Two:

In addition to the construction of new facilities for Station 1 in Kill Devil Hills, Station 4 in Southern Shores and the Dare MedFlight Hanger (Station 7) on Roanoke Island, several other EMS stations throughout Dare County will also undergo a series of renovations, including EMS Station 8 in Manns Harbor. In addition, a new station (EMS Station 9) will be constructed in Kitty Hawk. Updates for each of these projects can be found below. 

EMS Station 8 in Manns Harbor and a new EMS station (EMS Station 9) in Kitty Hawk

Start Date: April 2024
Expected Completion: TBD
Cost: Approximately $19.4 million

EMS Station 8 in Manns Harbor
Rendering of the new Manns Harbor EMS Station 8.

EMS Station 9 in Kitty Hawk
Rendering of the new Kitty Hawk EMS Station 9


FUTURE PHASES:

Phase 3: EMS Station 5 in Nags Head
Start Date: February 2025
Expected Completion: TBD
Cost: Approximately $10 million


Phase 4: EMS Station 2 (Manteo), EMS Station 3 (Frisco) and EMS Station 6 (Rodanthe)
Start Date: TBD
Expected Completion: TBD
Cost: TBD